Issue log template

Everything that is going wrong right now, with its impact, an owner and a next step. So problems get solved instead of discussed again every week.

Free, no signup. Opens in Excel, Google Sheets and Numbers.

Imports asRisks and issues

What is in the template

Example data. Delete it before you add your own.

Issue titleTypeCategoryImpactStatusActionOwnerDue dateProjectDescription
Payment provider test account is blockedIssueExternalHighMitigatingEscalate to the account manager and test with the sandbox meanwhileJoris Bakker2026-11-20Website relaunchCheckout cannot be tested until the account is unblocked
Client asks for two extra page templatesIssueScheduleMediumAnalyzingEstimate the work and send a change requestSanne de Vries2026-11-18Website relaunchNot in the signed scope, affects the build milestone
Pilot users cannot log in with single sign onIssueTechnicalHighMitigatingFix the identity provider settings with client ITLisa Smit2026-11-24CRM rolloutTwelve of thirty pilot users are blocked
Training room is double booked on 8 DecemberIssueOrganizationalLowResolvedMoved the session to the client officeSanne de Vries2026-11-13CRM rolloutSolved, kept for the record
Movers can only come one week laterIssueExternalMediumAcceptedStaff work from home for three extra daysTom Hendriks2026-12-11Office moveOffice handover date stays the same

How to use it

  1. 1

    Log an issue as soon as it affects the plan, the budget or the client. Small fixes that cost nobody time can stay out.

  2. 2

    Rate the impact and give it one owner. The owner drives the fix, they do not have to do all the work.

  3. 3

    Write the next action, not the whole solution, and give it a due date.

  4. 4

    Set the status to Resolved when it is fixed. Keep the row, it helps the next project avoid the same problem.

What each column means

Issue title
What is going wrong right now, in one line.
Type
Always Issue here. Vaizy keeps risks and issues in one register.
Category
What kind of problem it is.
Impact
How much it hurts the project, from Very low to Very high.
Status
Identified, Analyzing, Mitigating, Resolved or Accepted.
Action
The next step to solve it.
Owner
The one person who drives the fix.
Due date
When the action should be done.
Project
The exact project name. The import uses it to put each row on the right project.
Description
What happened and what it affects.

How to run an issue log

An issue is happening now

If it might happen, it is a risk and belongs in the risk register. If it already happened, it is an issue and needs an action, not a probability.

One owner per issue

Issues with two owners wait for each other. Pick one person who answers for it, even if a team does the work.

Escalate on impact, not on age

A High impact issue goes to the sponsor the same week. A Low impact issue that is old just needs a decision to accept it.

When the issue log stops being enough

An issue log shows problems, but not what they do to the plan. You still work out by hand which milestone slips and what it costs. In Vaizy risks and issues live in one register per project, linked to the milestones and budget they affect, and you see open issues across every project at once.

See risks and issues in Vaizy

Import it into Vaizy

  1. Start a free trial and open the import dialog from the dashboard.

  2. Drop in the file. Vaizy recognises the columns and maps them for you.

  3. Check the preview and import. Nothing is saved until you confirm.

Names in Owner and Assigned to link to team members with the same name or email. Import your team first, or the import lists the names it could not match.

Start your free trial

Questions about this template

A list of problems that are affecting a project right now, with their impact, who owns the fix, the next action and when it is due.

They can be, but they are closely linked: a risk that happens becomes an issue. Vaizy keeps both in one register with a Type field, and this template uses the same field.

Yes. Each row becomes an issue in the project you name, with its impact, status, action and owner. Vaizy places them in the same register as your risks.