Milestone tracker template

The moments that matter in each project, with their due date, status and progress. See at a glance which milestones are done, which are running and which are at risk.

Free, no signup. Opens in Excel, Google Sheets and Numbers.

Imports asMilestones

What is in the template

Example data. Delete it before you add your own.

MilestoneProjectPhaseStart dateDue dateStatusProgressDeliverables
Kickoff and discoveryWebsite relaunchPlanning2026-09-012026-09-18Completed100Stakeholder interviews, Sitemap, Content audit
Design sign offWebsite relaunchDesign2026-09-212026-10-23Completed100Wireframes, Visual design, Design system
Build and CMS setupWebsite relaunchDevelopment2026-10-262026-12-11In progress55Page templates, CMS setup, Forms
Content migrationWebsite relaunchDevelopment2026-11-162027-01-08In progress30Content mapping, Migration, Redirects
LaunchWebsite relaunchDeployment2027-01-112027-01-29Pending0Test report, Go live, Handover
Requirements and data modelCRM rolloutPlanning2026-10-052026-11-13Completed100Process maps, Data model, Field list
Pilot with sales teamCRM rolloutTesting2026-11-162027-01-22In progress40Pilot environment, Sales training, Feedback report

How to use it

  1. 1

    Write each milestone as a result someone can check, such as Design sign off, not as an activity.

  2. 2

    Add the project name exactly as it appears in your portfolio, so milestones from several projects can share one sheet.

  3. 3

    Update status and progress once a week, ideally just before your project meeting.

  4. 4

    List what gets handed over in the Deliverables column, separated by commas.

What each column means

Milestone
A point where something is finished and can be checked, such as Design sign off.
Project
The exact project name. The import uses it to put each row on the right project.
Phase
The stage it belongs to. Use the same phase names in every project.
Start date
When work towards it starts.
Due date
When it should be done.
Status
Pending, In progress, Completed, On hold or Cancelled.
Progress
How far along it is, from 0 to 100.
Deliverables
What is handed over at this milestone, separated by commas.

What makes a good milestone

A milestone is a result, not an activity

"Design signed off by the client" can be checked. "Working on design" cannot. If you cannot say when it is done, it is not a milestone.

Aim for one every two to six weeks

With fewer you hear about delays too late. With more the list turns into a task list that nobody keeps up to date.

Be strict about progress

Progress that sits at 90% for three weeks usually means the last part is the hard part. Ask what is left, not how far along it is.

When the tracker stops being enough

A tracker shows dates, not what a slip costs. When Design sign off moves two weeks, you still work out by hand which milestones, people and invoices move with it. Vaizy links each milestone to the team, hours and budget behind it, so you see the knock on effect straight away.

See milestone tracking in Vaizy

Import it into Vaizy

  1. Start a free trial and open the import dialog from the dashboard.

  2. Drop in the file. Vaizy recognises the columns and maps them for you.

  3. Check the preview and import. Nothing is saved until you confirm.

Start your free trial

Questions about this template

A list of the key moments in a project with their due dates, status and progress. It shows at a glance whether a project is on schedule.

A task is work someone does. A milestone is the result that work leads to. Track milestones here and leave the tasks to the people doing them.

Yes. Each row becomes a milestone with its dates, status and progress, and the Deliverables column turns into deliverables under that milestone.